building
expansion program

here are some details of the new building
expansion program.
the building expansion program essentially
replaces what was the phase 5 portion of the
Building Faith program. this new program
encompasses much more than the original phase 5
as it was originally presented.
this program is in response to issues originally
identified along with what was accomplished in
the original phases 1 - 4. it was decided to do
what we now call the building expansion
program last as it would be the most costly.
as with the original phases the main emphasis is
to honor God by giving Him our best and to
provide an inviting facility for visitors.
the three main areas to be addressed are:
 |
provide a clearly identified and inviting
main entry |
 |
design a large open area outside the
sanctuary for fellowship |
 |
plan for future needs in terms of
office/classroom space |
all exterior finishes will match current
building architectural details.
the following images and details are those
shared at the congregational meeting on january
20,2008; which were enthusiastically received.
floor plans
the floor plans are shown shaded to give
emphasis to the construction details on each
floor level in the church. actual construction
may or may not follow the shaded schemes. they
are simply shown for visual clarifications.

main level
- parking lot entry to the top

basement
level - parking lot to the top

second
level - parking lot to the top
exterior elevations

from wilson
avenue - new entry and addition to east

from south
parking lot - new entry and addition to east

from west -
new entry

from north
- new restrooms extension and stairways

from north
- new restrooms extension and stairways
details
this
will present the expansion in "Phases",
corresponding to the shaded colors on the floor
plans.
note
that some details may change and that all design
work is shown for information purposes.
phase
1 - main level
 |
approximately 1200 additional square feet
outside the sanctuary
|
 |
new men's and women's restrooms that are
handicap accessible
|
 |
extra wide stairs with interim landing
leading to Hall of Faith that will be heated
in the winter to prevent ice and snow
|
 |
removal of short wall just outside the
sanctuary |
 |
glass wall in administration office to
provide for better visibility and security
|
 |
coat storage is out of the way
|
 |
focused display area for bulletin board
information |
phase
1 - basement level
 |
large unfinished foundation area on the
north side of the church
|
 |
could provide for 2 additional classrooms
|
 |
access provide via hallway through current
classrooms |
 |
direct access door/stairs to playground area
from basement |
phase
2 - main level
 |
new main entry with double doors |
 |
large glass areas visually opening this area
from both the inside and the outside |
 |
utilizes the existing slope for drop off /
pickup |
 |
increases fellowship to approximately 2400
square feet outside the sanctuary |
 |
provides for a welcome / visitors
information center |
 |
additional focused display area for bulletin
board information |
 |
prayer room moved to second floor (phase 3
addition) |
 |
glass wall between sanctuary and old prayer
room space |
 |
section of casual seating with couches,
chairs, and tables; including a fireplace |
 |
removal of short wall just outside the
sanctuary |
 |
large glassed in library space which can
double as a conference / meeting room |
 |
old library goes away |
 |
pastor's office remodeled |
phase
2 - basement level
 |
large unfinished foundation area on the
south side of the church
|
 |
could provide for 3 additional classrooms or
one big room |
 |
access provide via hallway through current
classrooms |
phase
3 - main level
 |
removal of current entry from Wilson avenue
|
 |
provides for two additional office spaces
|
 |
provides for a large storage room
|
phase
3 - basement level
 |
provides for two additional classroom spaces
|
 |
provides for a storage room
|
phase
3 - second level
 |
provides for two additional office spaces
|
 |
provides for a large prayer room
|
|